PMP Exam Cheatsheet

PMP Deep Dive: Process & Business Environment Domains

🎯 PMP Deep Dive Guide

Process Domain (50%) & Business Environment Domain (8%)

⚙️ PROCESS DOMAIN

50% of Exam – 17 Key Tasks

Execution & Value Delivery Cluster
Task 1: Execute Project with Urgency
Exam Trap: “Stakeholder complains they didn’t know about issue” → Check communications management plan, was communication actually sent and received?
Procurement & Closure Cluster
Task 11: Plan & Manage Procurement

Make-or-Buy Analysis:

Consider: Cost, capacity, expertise, risk, control

Contract Types (MEMORIZE!):

Contract Type Risk Distribution When to Use
Fixed Price (FP/FFP) Seller has cost risk, buyer has performance risk Well-defined scope
Cost Plus (CPFF, CPIF) Buyer has cost risk, seller has less incentive to control costs Undefined scope, R&D
Time & Materials (T&M) Hybrid approach Scope unclear initially

Contract Closure:

  • Verify all work completed
  • Formal acceptance
  • Final payment
  • Lessons learned
Exam Insight: “Which contract type for undefined scope?” → T&M. “Which contract type minimizes buyer risk?” → Fixed Price.
Task 17: Plan & Manage Closure

Closure Activities:

  • Obtain formal acceptance from customer/sponsor
  • Transfer deliverables and ownership
  • Release resources (team members, equipment)
  • Archive documents and lessons learned
  • Celebrate success (recognize team contributions)

Final Report Includes:

  • Performance metrics
  • Budget variance
  • Lessons learned
  • Outstanding risks
Exam Scenario: “Project cancelled mid-way” → STILL perform closure activities! Document why, what was completed, lessons learned.
Task 12: Manage Project Artifacts

Key Concepts:

  • Configuration Management System: Version control, access control, audit trail
  • Document Types: Plans, reports, logs, registers, baselines, contracts, correspondence
  • Information Management: Who needs what information, when, in what format?
  • Agile Artifacts: Product backlog, sprint backlog, burndown charts, Definition of Done
Exam Tip: “Where would you find…” → Know which document contains what information.
Task 16: Ensure Knowledge Transfer

Knowledge Types:

  • Tacit Knowledge: Personal experience, insights (hard to document)
  • Explicit Knowledge: Documented procedures, templates (easy to share)

Knowledge Transfer Methods:

  • Documentation: Manuals, wikis, recorded demos
  • Training: Formal sessions, mentoring, shadowing
  • Communities of Practice: Expert networks, lunch-and-learns
Exam Context: “Team member leaving mid-project” → Document their knowledge, pair with other team member, update documentation.

📈 BUSINESS ENVIRONMENT DOMAIN

8% of Exam – 4 Key Tasks (Tests Strategic Thinking!)

Task 1: Plan & Manage Project Compliance Strategic

Compliance Categories:

  • Legal/Regulatory: GDPR, HIPAA, FDA, EPA, safety regulations
  • Industry Standards: ISO, IEEE, Six Sigma
  • Organizational Policies: Security, procurement, HR policies

Compliance Activities:

  • Identify applicable requirements early in planning
  • Build into design: Don’t treat as afterthought
  • Audit/verify: Regular compliance checks
  • Document evidence: Audit trail for regulators
Risk of Non-Compliance: Fines, legal liability, project shutdown, reputational damage.
Exam Scenario: “New data privacy law passed” → Assess impact, update requirements, implement controls, document compliance.
Task 2: Evaluate & Deliver Project Benefits/Value Critical!

Business Case:

Justifies project investment: ROI, NPV, payback period, strategic alignment

Benefits Types:

  • Tangible: Revenue increase, cost reduction, time savings
  • Intangible: Brand reputation, customer satisfaction, employee morale

Value Delivery Approach:

Approach Value Realization
Agile Incremental value delivery each iteration (highest-value features first)
Predictive Value often realized after project completion
Exam Insight: “Project on time/budget but stakeholders unhappy” → Delivered output but not outcome/benefits. Should have validated alignment throughout.
Task 3: Evaluate & Address External Business Changes

External Factors (PESTLE Analysis):

  • Political: Government changes, trade policies
  • Economic: Recession, inflation, currency fluctuation
  • Social: Demographic shifts, cultural trends
  • Technological: New technologies, obsolescence
  • Legal: New laws, court decisions
  • Environmental: Climate change, natural disasters

Adaptation Strategies:

  • Minor Change: Adjust within current plan
  • Major Change: Re-evaluate business case, may need to pivot or cancel
Exam Scenario: “Major competitor releases similar product” → Assess impact on business case, may need to accelerate timeline or differentiate features.
Task 4: Support Organizational Change

Change Management Models:

  • ADKAR: Awareness → Desire → Knowledge → Ability → Reinforcement
  • Kotter’s 8 Steps: Create urgency → Build coalition → Form vision → Communicate → Remove obstacles → Create wins → Build on change → Anchor in culture

Resistance to Change:

  • Common Reasons: Fear of unknown, loss of control, additional work, threat to expertise
  • Strategies: Communication, involvement, education, support, negotiation

Important Distinctions:

  • Transition: Moving from current to future state (project focus)
  • Transformation: Fundamental change in operations/culture (broader)
Sustainability: Ensure changes stick after project ends (training, reinforcement, leadership support).
Exam Scenario: “Employees refusing to use new system” → This is change management issue, not technical. Need training, communication, address concerns, show benefits.

🎯 Cross-Domain Integration Points

Understanding how domains connect is crucial for exam success:

  • Methodology Selection (Process) ↔ External Changes (Business): Agile better handles volatile external environment
  • Stakeholder Engagement (Process) ↔ Organizational Change (Business): Engaged stakeholders = successful adoption
  • Benefits Delivery (Business) ↔ Execution (Process): Must execute with value-focused urgency
  • Compliance (Business) ↔ Quality/Scope (Process): Compliance requirements shape quality standards and scope
  • Risk Management (Process) ↔ External Changes (Business): External changes create new risks

📚 Study Strategies for These Domains

Process Domain (50%):

  • Focus on EVM formulas, change control process, risk response strategies
  • Understand differences: QA/QC, leveling/smoothing, threats/opportunities
  • Practice scenario questions: “What should PM do FIRST/NEXT?”
  • Key formula to memorize:
    • Communication channels: n(n-1)/2
    • CPI = EV/AC
    • SPI = EV/PV
    • Three-point estimate: (O + 4M + P) / 6

Business Environment (8%):

  • Think strategically: business value, organizational fit, change adoption
  • Connect projects to business outcomes, not just outputs
  • Understand PM’s role in broader organizational context
  • Remember: Project success = Delivered value + Stakeholder satisfaction

Common Exam Traps (MEMORIZE!):

  • “Gold plating” is ALWAYS wrong (even if team has time)
  • Always follow formal processes (change control, escalation)
  • When in doubt: Communicate and Document
  • PM facilitates but doesn’t make all decisions (sponsor, CCB, team have roles)
  • Risk ≠ Issue: Risk is future/uncertain, Issue is present/certain
  • Don’t confuse outputs (deliverables) with outcomes (benefits)

Exam Question Patterns:

If Question Says… Answer Usually Involves…
“What should PM do FIRST?” Assess, analyze, review documentation before acting
“Requirements are unclear” Agile/iterative approach
“Fixed-price contract” Predictive approach with tight scope control
“Stakeholder requests change” Follow change control process
“Team conflict” Address directly, don’t ignore or escalate immediately
“Behind schedule” Analyze critical path before adding resources
Quick Reference: Must-Know Comparisons

Risk Response Strategies:

Strategy For Threats (Negative) For Opportunities (Positive)
Eliminate/Ensure Avoid Exploit
Reduce/Increase Mitigate Enhance
Shift responsibility Transfer Share
Acknowledge Accept Accept

Power vs. Authority:

Type Source Example
Formal/Legitimate Position/title PM assigned by organization
Reward Ability to give rewards Performance bonuses
Penalty/Coercive Ability to punish Least effective, use sparingly
Expert Knowledge/skills Technical expertise
Referent Respect/charisma Most effective long-term

Why it matters: This isn’t just about “doing the work”—it’s about maintaining momentum and delivering incremental value quickly.

Key Concepts:

  • Velocity (Agile): Track team capacity and throughput
  • Critical Path Management (Predictive): Focus resources on activities that directly impact timeline
  • Value Stream Mapping: Eliminate waste and non-value-added activities
Exam Trap: Questions may present scenarios where you must balance speed vs. quality—remember urgency ≠ rushing; it means purposeful, efficient execution.
Real Scenario: Team wants to add “nice-to-have” features → You must redirect focus to MVP/critical features that deliver business value NOW.
Task 13: Determine Methodology Often Tested!

This is foundational – wrong methodology = project struggles

Decision Factors:

  • Requirements Clarity: Fixed? → Predictive | Evolving? → Agile
  • Organizational Culture: Command-and-control? → Predictive works better initially
  • Risk Tolerance: Low tolerance? → Predictive (more planning) | High? → Agile (rapid adaptation)
  • Regulatory Environment: Highly regulated (pharma, aerospace)? → Predictive with heavy documentation

Hybrid Approach:

Most common in reality! Use Predictive for infrastructure/compliance work, Agile for software/innovation.

Exam Insight: Look for keywords like “requirements are unclear” (Agile), “fixed-price contract” (Predictive), “regulatory approval needed” (Predictive with gates).
Task 14: Establish Governance

Governance ≠ bureaucracy: It’s about decision rights and accountability.

Key Structures:

  • Steering Committee: Strategic decisions, major changes, escalations
  • Change Control Board (CCB): Evaluates and approves/rejects change requests
  • Project Management Office (PMO): Standards, templates, oversight
  • Decision Gates: Stage-gate reviews for phase transitions (especially in Predictive)
Exam Scenario: Who approves what? Small change to deliverable? → PM. Major scope change affecting budget? → Sponsor/Steering Committee.
Planning Integration Cluster
Task 9: Integrate Planning Critical!

The “master plan”: All subsidiary plans must align and support each other.

Key Integration Points:

  • Schedule ↔ Resources: Do you have the right people when activities are scheduled?
  • Budget ↔ Scope: Is funding allocated to all scope items?
  • Risk ↔ Schedule: Are risk response activities scheduled and funded?
  • Quality ↔ Cost: Are quality activities (testing, reviews) budgeted and scheduled?
Common Failure: Plans created in silos that contradict each other.
Exam Pattern: “Which plan should be updated FIRST?” → Usually the integrated project management plan, then subsidiary plans.
Task 5: Plan & Manage Budget/Resources

Beyond spreadsheets: This is about optimization and forecasting.

Key Estimating Techniques:

Technique Description Accuracy
Bottom-up Aggregate from work package level Most accurate
Analogous Use historical data from similar projects Faster, less accurate
Parametric Mathematical model (e.g., $500/sq ft) Medium accuracy
Three-point (O + 4M + P) / 6 Good for uncertainty

Earned Value Management (EVM) Formulas:

  • PV (Planned Value): What should we have spent?
  • EV (Earned Value): Value of work actually completed
  • AC (Actual Cost): What we actually spent
  • CPI (Cost Performance Index) = EV/AC
    <1 = over budget, >1 = under budget
  • SPI (Schedule Performance Index) = EV/PV
    <1 = behind schedule, >1 = ahead

Resource Leveling vs. Smoothing:

  • Leveling: May extend schedule to avoid resource overallocation
  • Smoothing: Maintains original schedule, adjusts activities within float
Exam Trap: “Team member available part-time” → Must account for productivity loss (context switching).
Task 6: Plan & Manage Schedule

Critical Concepts:

  • Critical Path Method (CPM): Longest path through network = shortest project duration
  • Total Float: Can slip without delaying project
  • Free Float: Can slip without delaying successor activities

Schedule Compression:

Method Action Impact
Fast-tracking Do activities in parallel Increases risk
Crashing Add resources to critical path Increases cost
Exam Scenario: “Project is behind schedule, what do you do FIRST?” → Analyze critical path and float, don’t just throw resources at it.
Task 8: Plan & Manage Scope

The Scope Hierarchy:

  1. Project Charter: High-level project description
  2. Scope Statement: Detailed description of project and deliverables
  3. WBS (Work Breakdown Structure): Decomposed deliverables into work packages
  4. WBS Dictionary: Detailed description of each WBS element

Important Distinctions:

  • Scope Validation: Customer formally accepts completed deliverables (different from quality control which is internal verification)
  • Scope Creep: Uncontrolled changes/additions
  • Gold Plating: Adding extra features without approval (even if “free”—still increases risk and maintenance)
Exam Insight: “Stakeholder requests additional feature” → Don’t just add it! Follow change control process, assess impact.
Task 7: Plan & Manage Quality

Quality vs. Grade:

  • Quality: Meeting requirements (defect-free)
  • Grade: Category/features (economy vs. luxury car—both can be high quality)

Cost of Quality:

  • Prevention Costs: Training, process improvement (BEST investment)
  • Appraisal Costs: Testing, inspections
  • Failure Costs: Rework, warranty, liability (MOST expensive)

Key Concepts:

  • Quality Assurance (QA): Process-focused, prevents defects
  • Quality Control (QC): Product-focused, detects defects
Exam Trap: “Customer wants lower cost, suggests reducing testing” → Explain cost of quality, reducing prevention is most expensive long-term.
Change & Risk Management Cluster
Task 10: Manage Project Changes Heavily Tested!

Integrated Change Control Process:

  1. Change request submitted (anyone can submit)
  2. PM analyzes impact (scope, schedule, cost, quality, risk, resources)
  3. Change Control Board (CCB) reviews and decides
  4. Approved changes → Update baselines and plans
  5. Communicate decision to stakeholders

Important Concepts:

  • Baseline Management: Scope, schedule, cost baselines are formal references—changes must be approved
  • Configuration Management: Version control for deliverables, documents, code
  • Agile Approach: Changes welcomed in backlog, prioritized by Product Owner, incorporated in next iteration
Exam Scenario: “Team member suggests improvement” → Document as change request, analyze impact, get approval (even if it seems minor).
Task 3: Assess & Manage Risks High-Value Topic!

Risk ≠ Issue:

  • Risk: Uncertain event that MAY occur (future)
  • Issue: Problem that HAS occurred (present)

Risk Management Process:

  1. Identify: Brainstorming, SWOT, checklist, expert interviews
  2. Analyze Qualitatively: Probability × Impact matrix (High/Medium/Low)
  3. Analyze Quantitatively: Monte Carlo, decision tree, EMV
  4. Plan Responses:
    • Threats: Avoid, Mitigate, Transfer, Accept
    • Opportunities: Exploit, Enhance, Share, Accept
  5. Implement Responses: Execute planned strategies
  6. Monitor: Track identified risks, identify new risks

Reserve Types:

  • Contingency Reserve: For KNOWN risks (identified in risk register)
  • Management Reserve: For UNKNOWN risks (unidentified risks)
Exam Insight: “Supplier may go bankrupt” → Threat. Response? Transfer (use different supplier) or Accept (develop backup plan).
Task 15: Manage Project Issues

Issue Management:

  • Issue Log/Register: Tracks all current problems
  • Issue Prioritization: Impact + urgency determines order
  • Escalation Criteria: When does issue go to sponsor/steering committee?
  • Root Cause Analysis: Don’t just treat symptoms—find and fix underlying cause (5 Whys, Fishbone diagram)
Exam Distinction: Don’t confuse with risk management—issues are happening NOW and need immediate action.
Stakeholder & Communication Cluster
Task 4: Engage Stakeholders

Stakeholder Analysis:

  • Power/Interest Grid: High power/high interest = Manage Closely
  • Influence: Can they help or hurt the project?
  • Impact: How much does project affect them?

Engagement Levels:

Unaware → Resistant → Neutral → Supportive → Leading

Strategy: Move stakeholders toward “Supportive” or “Leading”

Exam Scenario: “Influential stakeholder opposes project” → Don’t ignore! Engage early, understand concerns, find win-win solutions.
Task 2: Manage Communications

Communication Channels Formula:

n(n-1)/2 where n = number of people

  • 5 people = 10 channels
  • 10 people = 45 channels (complexity explodes!)

Communication Methods:

Method Description Best For
Interactive Meetings, calls Complex topics
Push Email, reports Sender controls distribution
Pull Intranet, wikis Receiver decides when to access